Reconstruction of HVAC in food court in ESC

Case Study
Building services engineering
The client:
CBRE
Year and duration of implementation:
2023
3 months
Location:
Banská Bystrica

The description of a project

Task

As part of the modernization of the food court in the Europa SC, the client approached us with a request for a comprehensive reconstruction of the technological parts – while the facility remained fully running.

The project included a change and renovation of the systems:

  • Heating, ventilation, and air conditioning (HVAC)
  • Electrical installation (ELI)
  • Measurement and regulation (M and R)

Solution

The realisation took place without disrupting the normal operation of the center. This required:

  • Thorough coordination with the facility operator and tenants
  • Precisely timed stage replacements of both outdoor and indoor units of HVAC routes.
  • Compliance with the highest safety and operational standards

The comfort of visitors and tenants of the center was taken into consideration when the work was carried out.

The result

During three months:

  • We increased efficiency and reliability of systems by replacing technological equipment
  • We ensured modern, cost-saving and sustainable operation of the food court
  • We disrupted the operation of the facility very little thanks to precise preparation and team coordination

“Renovations during full operation are among the most difficult types of projects. They require not only technical precision but also perfect planning. We managed to do this at Europa SC thanks to our experienced team and fair cooperation with the client.”